Fire compartmentation survey and remediation, 22-storey residential tower, Birmingham

DefendX completed a full compartmentation survey and passive fire-stopping remediation on a 22-storey tower under Building Safety Act Accountable Person obligations.

Client
Registered housing provider
Division
Fire Protection
Year
2025
Result
124
Home/Case studies/Fire compartmentation survey and remediation, 22-storey residential tower, Birmingham
The brief

DefendX completed a full compartmentation survey and passive fire-stopping remediation on a 22-storey tower under Building Safety Act Accountable Person obligations.

01

The challenge

A registered housing provider operating a 22-storey residential tower in Birmingham required a full compartmentation survey and remediation programme as part of its Building Safety Act Accountable Person obligations, to be completed while the building remained occupied.

02

Our approach

DefendX deployed a four-person survey team to complete a floor-by-floor compartmentation assessment across all 22 floors. The survey identified 124 penetration deficiencies, and DefendX produced a phased remediation programme completed floor-by-floor with minimum disruption to residents.

03

The result

All 124 penetrations were remediated to specification, with a full compartmentation record handed to the Accountable Person for the building's Safety Case. The tower remained occupied throughout, with no more than one floor affected by works at any time.

Divisions involved

The lines that ran this contract.

Next step

Have a contract that needs the same.

Tell us the site, the programme and the lines you need covered. We come back with a mobilisation plan and a quote.

Operations desk
Head officeCoventry CV3
HoursMon to Fri, 08:00 to 17:00